Millet Strip Deck Replacement

Project type

Bridge Repairs

Date

2024

Location

Millet, AB

Owner & Client: Town of Millet
Schedule: Actual: 2 days

Snake Bridge, north of Millet, Alberta, provides access to residential properties across Eyot Creek. An inspection revealed significant deterioration of the timber strip deck wearing surface and old timber piles in the creek obstructing flow and catching drift.

Access BridgeWorks replaced the timber subdeck and strip deck, restoring the bridge’s structural integrity and durability. They also removed the abandoned timber piles, improving hydraulic flow and reducing future obstruction risks. Completed in just two days, the project showcased Access BridgeWorks’ efficiency and expertise in small-scale bridge repairs.