top of page

Create Your First Project

Start adding your projects to your portfolio. Click on "Manage Projects" to get started

Summit Lake OH Bridge Rehabilitation

Project type

Bridge Rehabilitation and Maintenance

Date

2024–2025

Location

Revelstoke, BC

Owner & Client: British Columbia Ministry of Transportation and Infrastructure

Schedule: Planned: 8 months | Actual: 6 months
Cost: $4,400,000.00

The Summit Lake Overhead Bridge, a 13-span, 144-meter structure built in 1955, carries Highway 1 over a CPKC rail line and the Eagle River, a vital salmon spawning habitat. Access BridgeWorks was awarded the rehabilitation contract in September 2024, tackling 67 UHPC beam-end repairs, deck joint replacements, pier strengthening, and 310 m² of concrete repairs, all while implementing strict environmental protections above an active rail line.

To minimize disruption, traffic was managed with single-lane alternating configurations at night, with steel road plates restoring two-way flow during the day. Despite a late-season start, the project was completed two months ahead of schedule, earning Access BridgeWorks a nomination for British Columbia’s Contractor of the Year Award for exceptional performance under complex conditions.

bottom of page